Troubleshooting Heat Trace Alarms - Procedure
This is EHT Groups internal technical procedure on how to field troubleshoot various heat trace alarms.
1
1.1 Purpose
This procedure describes the steps required to safely and effectively identify and troubleshoot failures in an electrical heat trace circuit.
The Purpose is to provide EHT Group EHT Technicians general guidance to ensure that EHT circuits and the associated insulation systems are functioning as designed and provide adequate protection to the equipment on which they are installed.
1.2 Precautions
Only qualified electricians to perform their respective tasks
Review application reference documents for the task
A safe work permit is required for this task and must be signed by the area Operator
Complete a Field Level Hazard Assessment (FLHA) with all personnel involved with the job before starting the work
Ensure EHT circuit is in good condition and operating as designed before commencing work.
Arc-flash rated coveralls must be worn.
Follow all arc flash safe work procedures and PPE requirements as required by this task.
1.3 Roles & Responsibilities
For best results 2 EHT technicians are required with access to ATCOM+ while troubleshooting.
2. Procedure
2.1 Prioritize Walk Downs
Ensure highest priority walk down is completed first. This situation arises if multiple walk downs are received at once.
2.2 Visual Inspection
Review EHT Isometric and panel schedule to determine location of EHT Circuit
Complete visual inspection of entire EHT circuit – Verify the following match the EHT isometric:
- Piping size and orientation
- Piping adder location, quantity and size
- EHT component location, part number and quantity (Includes RTDs, power box, junction/splice boxes and end kits)
- Component install is installed as per Suncor Standard Detail (when available and not covered by insulation)
- Insulation is all installed
- Insulation type and size is correct
- Insulation blankets are correct size and tightly installed
Record all findings on EHT Alarm Response Check Sheet Document
- Identify on EHT Isometric if any section is not accessible and what is required to access
2.3 Identify Troubleshooting/Repair Steps
|
If Alarm Is … |
Then … |
|
Low Temperature |
Go to 2.4 |
|
RTD Failure |
Go to 2.5 |
|
Ground Fault |
Go to 2.6 |
|
Switch Failure |
Go to 2.7 |
|
Low Load |
Go to 2.8 |
2.4 Low Temperature Alarm Procedure
|
Responsibility |
Step |
Action |
||||||
|
EHT Maintenance Electrician |
1 |
At the Control Panel (PJ) complete the following tests: · Identify EHT circuit and RTDs · Verify all panel wiring for RTD(s) are correct · Measure Resistance of all RTDs connected to EHT circuit |
||||||
|
EHT Maintenance Electrician |
2 |
Reverify all panel wiring for HTC and RTD(s) is correct |
||||||
|
EHT Maintenance Electrician |
3 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
4 |
Relocate to EHT circuit RTD using coordinates on EHT isometric |
||||||
|
EHT Maintenance Electrician |
5 |
At the EHT Circuit RTD complete the following tests: · Verify all control connections are correct and terminated · Measure Resistance of RTD · Verify all control connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
6 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
7 |
|
||||||
|
EHT Maintenance Electrician |
8 |
Relocate to next sequential RTD (ex. RTD2) using EHT Isometric coordinates |
||||||
|
EHT Maintenance Electrician |
9 |
At the EHT Circuit RTD complete the following tests: · Verify all control connections are correct and terminated · Measure Resistance of RTD · Verify all control connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
10 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
11 |
|
||||||
|
EHT Maintenance Electrician |
12 |
Ensure EHT Alarm Response Check Sheet Document is complete |
||||||
|
EHT Maintenance Electrician |
13 |
Go to Step 12 |
2.5 Ground Fault Alarm
|
Responsibility |
Step |
Action |
||||||
|
EHT Maintenance Electrician |
1 |
At the Control Panel (PJ) complete the following tests: · Verify all panel wiring for HTC and RTD(s) are correct · Identify EHT circuit and RTDs · Measure EHT circuit resistance and use EHT isometric to verify value matches design resistance · Measure Insulation Resistance of EHT Circuit – Click here for testing method and minimum requirements · Measure EHT circuit voltage and verify it matches EHT Isometric · Measure EHT circuit current and verify it matches EHT Isometric |
||||||
|
EHT Maintenance Electrician |
2 |
Reverify all panel wiring for HTC and RTD(s) is correct |
||||||
|
EHT Maintenance Electrician |
3 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
4 |
Relocate to EHT circuit power box using coordinates on EHT isometric |
||||||
|
EHT Maintenance Electrician |
5 |
At the EHT Circuit Power Box complete the following tests: · Verify all power connections are correct and terminated · Measure EHT cable(s) resistance and use EHT isometric to verify value matches cables(s) design resistance · Measure Insulation Resistance of EHT cables(s) – Click here for testing method and minimum requirements · Measure EHT cables(s) voltage and verify it matches EHT Isometric · Measure EHT cables(s) circuit current and verify it matches EHT Isometric · Verify all power connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
6 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
7 |
|
||||||
|
EHT Maintenance Electrician |
8 |
Relocate to next sequential power, splice or junction box (ex. SB2) |
||||||
|
EHT Maintenance Electrician |
9 |
At the EHT power, splice or junction box complete the following tests: · Verify all power connections are correct and terminated · Measure EHT cable(s) resistance and use EHT isometric to verify value matches cables(s) design resistance · Measure Insulation Resistance of EHT cables(s) – Click here for testing method and minimum requirements · Measure EHT cables(s) voltage and verify it matches EHT Isometric · Measure EHT cables(s) circuit current and verify it matches EHT Isometric · Verify all power connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
10 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
11
|
|
||||||
|
EHT Maintenance Electrician |
12 |
Ensure EHT Alarm Response Check Sheet Document is complete |
||||||
|
EHT Maintenance Electrician |
13 |
Go to Step 12 |
2.6 Switch/Relay Fail
|
Responsibility |
Step |
Action |
||||||
|
EHT Maintenance Electrician |
1 |
At the Control Panel (PJ) complete the following tests: · Verify all panel wiring for HTC is correct · Measure EHT circuit voltage and verify it matches EHT Isometric · Test operation of SSR o Communicate with EHT Software Technician to test HTC (Turn ON and OFF) · Test operation of HTC Module o Communicate with EHT Software Technician to test HTC (Turn ON and OFF) · Measure EHT circuit current and verify it matches EHT Isometric |
||||||
|
EHT Maintenance Electrician |
2 |
Reverify all panel wiring for HTC and RTD(s) is correct |
||||||
|
EHT Maintenance Electrician |
3 |
Verify programming of EHT circuit is set back to design parameters |
||||||
|
EHT Maintenance Electrician |
4 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
5 |
Relocate to EHT circuit power box using coordinates on EHT isometric |
||||||
|
EHT Maintenance Electrician |
6 |
At the EHT Circuit Power Box complete the following tests: · Verify all power connections are correct and terminated · Measure EHT cables(s) circuit current and verify it matches EHT Isometric · Verify all power connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
7 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
8 |
|
||||||
|
EHT Maintenance Electrician |
9 |
Relocate to next sequential power, splice or junction box (ex. SB2) |
||||||
|
EHT Maintenance Electrician |
10 |
At the EHT power, splice or junction box complete the following tests: · Verify all power connections are correct and terminated · Measure EHT cables(s) circuit current and verify it matches EHT Isometric · Verify all power connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
11 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
12
|
|
||||||
|
EHT Maintenance Electrician |
13 |
Ensure EHT Alarm Response Check Sheet Document is complete |
||||||
|
EHT Maintenance Electrician |
14 |
Go to Step 12 |
2.7 Low Current Alarm
|
Responsibility |
Step |
Action |
||||||
|
EHT Maintenance Electrician |
1 |
At the Control Panel (PJ) complete the following tests: · Verify all panel wiring for HTC and RTD(s) are correct · Identify EHT circuit and RTDs · Measure EHT circuit resistance and use EHT isometric to verify value matches design resistance · Measure Insulation Resistance of EHT Circuit – Click here for testing method and minimum requirements · Measure EHT circuit voltage and verify it matches EHT Isometric · Measure EHT circuit current and verify it matches EHT Isometric · Test operation of SSR o Communicate with EHT Software Technician to test HTC (Turn ON and OFF) · Test operation of HTC Module o Communicate with EHT Software Technician to test HTC (Turn ON and OFF) |
||||||
|
EHT Maintenance Electrician |
2 |
Reverify all panel wiring for HTC and RTD(s) is correct |
||||||
|
EHT Maintenance Electrician |
3 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
4 |
Relocate to EHT circuit power box using coordinates on EHT isometric |
||||||
|
EHT Maintenance Electrician |
5 |
At the EHT Circuit Power Box complete the following tests: · Verify all power connections are correct and terminated · Measure EHT cable(s) resistance and use EHT isometric to verify value matches cables(s) design resistance · Measure Insulation Resistance of EHT cables(s) – Click here for testing method and minimum requirements · Measure EHT cables(s) voltage and verify it matches EHT Isometric · Measure EHT cables(s) circuit current and verify it matches EHT Isometric · Verify all power connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
6 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
7 |
|
||||||
|
EHT Maintenance Electrician |
8 |
Relocate to next sequential power, splice or junction box (ex. SB2) |
||||||
|
EHT Maintenance Electrician |
9 |
At the EHT power, splice or junction box complete the following tests: · Verify all power connections are correct and terminated · Measure EHT cable(s) resistance and use EHT isometric to verify value matches cables(s) design resistance · Measure Insulation Resistance of EHT cables(s) – Click here for testing method and minimum requirements · Measure EHT cables(s) voltage and verify it matches EHT Isometric · Measure EHT cables(s) circuit current and verify it matches EHT Isometric · Verify all power connections are correct and terminated |
||||||
|
EHT Maintenance Electrician |
10 |
Record all findings and measurements on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
11
|
|
||||||
|
EHT Maintenance Electrician |
12 |
Ensure EHT Alarm Response Check Sheet Document is complete |
||||||
|
EHT Maintenance Electrician |
13 |
Go to Step 12 |
2.8 Repair & Progress
|
Responsibility |
Step |
Action |
||||||
|
EHT Maintenance Electrician |
1 |
|
||||||
|
EHT Maintenance Electrician |
2 |
Complete required repair to resolve alarm/deficiency |
||||||
|
EHT Maintenance Electrician |
3 |
Verify operation of circuit with EHT Software Technician |
||||||
|
EHT Maintenance Electrician |
4 |
Record work completed on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
5 |
Go to Step 13 |
||||||
|
EHT Maintenance Electrician |
7 |
|
||||||
|
EHT Maintenance Electrician |
8 |
Complete required work to temporarily resolve/mitigate alarm/deficiency |
||||||
|
EHT Maintenance Electrician |
9 |
Record work completed on EHT Alarm Response Check Sheet Document |
||||||
|
EHT Maintenance Electrician |
10 |
Identify and record what is required to resolve alarm & notify supervisor: · Time required · Permit requirements · Material required · Access · Trade Support · Work involved |